GATE LNG Receiving Terminal

Challenge
Construction of two jetties for receiving Liquefied Natural Gas (LNG).
Our solution
-
Supply and piling of 64 steel tube piles Ø1420 mm and 45 piles Ø1220 mm
-
Supply and erection of 2 access trestles and pipe racks
-
Construction of 2 concrete decks (23x36 m +7.5 m NAP)
-
Construction of 2 concrete superstructures up to +17.5 m NAP
-
Supply and erection of multiple steel platforms, 4 staircases and 2 firefighting monitoring and lighting towers
-
Erection of 8 LNG unloading arms and 2 gangway towers
-
Supply, piling and assembly of 22 steel tube dolphin piles Ø2800 mm
-
Supply and erection of 700 m walkways (Ø1220 mm)
-
Supply and installation of lighting, cable trays and earthing